UTU-69125-65 moves Red Wash Highway away from the river, raises and widens it, and adds wildlife timing rules including yellow-billed cuckoo nesting season.
The story so far
The record retold in plain words, start to finish. Each paragraph links to the moments it draws on.
Uintah Transportation Special Service District is rebuilding Red Wash Road in Uintah County. In March 2025, the County Commission approved a federal right-of-way amendment to move, raise and widen the road under wildlife timing rules. According to an April 2025 recording, staff reviewed an original $8,532,000 project budget funded by a state grant, district cash and county B-road money. In August 2025, staff reported that an Army Corps permit was delaying bid-ready plans, according to the recording.
According to the December 2025 recording, the district advertised the project with an updated cost estimate above its existing funding. In January 2026, the board awarded an $11,373,733.50 base contract to Burdick Materials, with upgraded materials subject to available funding. After a February 2026 hearing, the board adopted an amended budget and raised the engineering contract for permitting and design.
In March 2026, staff reported finding a shallow Williams gas pipeline needing potholing, survey work and redesigns. The road district approved a potholing change order and voted to seek reimbursement from Williams. The next month, a presenter told the state Community Impact Board that inflation and federal permit delays raised costs. State board minutes record approval of a supplemental $3,792,000 grant and a $1,100,000 loan.
In May 2026, the district approved a $1,655,313 change order; posted district minutes include rock work and a gas-line road shift. In June, it approved a notice of intent to issue a funding bond. Its posted July 2026 minutes put the contract at about $13.02 million. The July recording shows potential litigation involving Williams went to closed session. In August, the district passed the final bond resolution, according to the recording. The record we have doesn't show whether Williams paid any costs or whether a lawsuit followed.
According to the September 2026 recording, culverts held in a storm while some riprap washed out. In October 2026, the recording shows the district agreed to a stilling basin change. That month, according to the county recording, the County Commission pledged not to impair the district's mineral lease revenues behind the bond. In the same recording, commissioners gave the district a limited joint interest in the road, which the county will keep maintaining.
As of November 2026, the recording shows no district action on rain-silted culverts and ditches, and the stilling basin change order remains due back. According to the recordings, riprap, striping and the Jensen Water line tie-in remain to be finished, and the district plans a 2027 budget hearing in December.